•Perform all work as per Canadian Electrical Code, OH&S Regulations, & company policies.
•Ensure proper PPE (steel toed boots, coveralls, safety glasses, hard hat, and H2S monitor).
•Identify all hazards (pressure, H2S gas, open valves).
•Lock & tag as per lockout procedure.
•Apply unit brake.
•Have operator present if possible.
•Close all valves, ratigans, etc., as required.
•Bleed off pressure as required.
•Disconnect as per wiring & maintenance procedure.
•Re-install & wire new presco.
•Re-open valves where required.
•Remove lockout & brakes.
•Reactivate well.